Marine Investigation Report M99L0011

Compressor bursting on the container ship
"CANMAR SPIRIT"
port of Montreal, Quebec

The Transportation Safety Board of Canada (TSB) investigated this occurrence for the purpose of advancing transportation safety. It is not the function of the Board to assign fault or determine civil or criminal liability. This report is not created for use in the context of legal, disciplinary or other proceedings. See Ownership and use of content.

Summary

On 27 January 1999, the "CANMAR SPIRIT" was upbound in the Port of Montreal, Quebec, making way towards section 78 for berthing and ensuing cargo operations.

As a normal part of the duties during manoeuvring, a member of the engine-room crew was detailed to start two of the ship's main air compressors. After having started the No. 1 compressor without incident, he proceeded to initiate the start-up of the No. 3 compressor. During the start-up sequence, a sudden and violent over-pressurization occurred within the compressor. Damage to the compressor included burst cooler tubes in the second-stage (after) cooler, burst compressor casing in way of the cooling water chamber, and a flayed flexible delivery air line. The second-stage air cooler cover also burst and fragments of this piece were projected outward in a shrapnel-like fashion, seriously injuring the crew member.

As the "CANMAR SPIRIT" had not yet berthed, a harbour tug was used to evacuate the injured crew member under the supervision and assistance of trained ambulance technicians. The crew member was later pronounced dead at the hospital.

The Board determined that the No. 3 compressor on the "CANMAR SPIRIT" experienced a severe and near instantaneous over-pressurization due to the system delivery valve remaining closed while the compressor was started. This omission, combined with the malfunctioning air relief valves, created a closed circuit in which certain components of the compressor could not withstand the ever-increasing pressure. A factor contributing to the accident was the less-than-adequate maintenance of non-return valves.

1.0 Factual Information

1.1 Particulars of the Vessel

Name "CANMAR SPIRIT"
Official number 341333
Port of registry Hong Kong
Flag Hong Kong (Special Administrative Region/China)
Type Container Ship
Gross TonsFootnote 1 15647
Length 167 m
Draught Forward: 6.46 m Aft: 7.26 m
Built 1970
Propulsion B&W turbo-charged eight-cylinder diesel engine, 11,100 kW
Cargo General cargo in containers
Crew 23
Passengers None
Managers Split Ship Management Ltd., Croatia
Owner(s) Canada Maritime Ltd., Bermuda

1.1.1 Description of the Vessel

The "CANMAR SPIRIT" is a 793 twenty-foot equivalent units (TEU)Footnote 2 container ship with four holds. The accommodation and machinery space are located aft. She is a regular caller at the Port of Montreal being on the North Atlantic trade route between Europe and North America, with an average service speed of 16.5 knots.

Launched in 1971 as the "CP TRADER", the vessel has seen a number of management and name changes. In 1982 she was renamed "ANDES TRADER", in 1986, "SAN LORENZO" and in 1994, "CANMAR SPIRIT".

1.2 History of the Voyage

On the afternoon of 18 January 1999, the "CANMAR SPIRIT" left Lisbon, Portugal, bound for Montreal. By the early afternoon of 27 January 1999, after an uneventful ocean passage, the vessel was approaching section 78 in the Port of Montreal to berth and commence cargo operations.

In the engine-room, the crew had been mustered to manoeuvring stations and were going about their various tasks. The chief engineer was present in the control room with the officer of the watch (OOW). At approximately 1345 eastern standard time,Footnote 3 the duty greaser was detailed to start up main air compressors Nos. 1 and 3. After starting the No. 1 compressor without incident, he proceeded to start the No. 3 compressor. Shortly after the initiation of the start-up procedure, at approximately 1400, a sudden and violent over-pressurization occurred within the compressor. An explosion-like noise was heard throughout the vessel and a white vapour was observed in the vicinity of the compressor by the crew members in the control room. The OOW went immediately to the scene of the accident and saw the duty greaser walking uneasily and then collapsing close to the No. 1 compressor, approximately eight metres from the scene of the accident. It would appear that the victim was in the process of closing the first- and second-stage purge drain valves when the over-pressurization occurred. The act of closing the purge drain valves positioned him near and just slightly to the right of the second-stage air cooler cover. The complete and violent failure of this piece of equipment during the over-pressurization of the compressor caused serious injuries to the duty greaser that later proved to be fatal.

First aid was administered to the injured crew member where he lay by the ship's personnel. Montreal Marine Communications and Traffic Services was advised of the situation and the tug "OCEAN INTREPID", with ambulance technicians on board, was called to the scene immediately. By 1418, the ambulance technicians had boarded the "CANMAR SPIRIT" by way of the tug and were administering first aid to the victim. At approximately 1455, the injured crew member was evacuated via the tug ashore, and then to a local hospital under the supervision and assistance of the ambulance technicians.

Once the injured crew member had been evacuated, the berthing operation of the "CANMAR SPIRIT" was successfully completed. Upon arrival at the hospital, the injured crew member was pronounced dead by the hospital authorities.

1.3 Injuries to Persons

Crew Passengers Others Total
Fatal 1 - - 1
Missing - - - -
Serious - - - -
Minor/None 22 - - 22
Total 23 - - 23

It has been established that the duty greaser died as a result of injuries sustained from fragments of metal projected at high velocity. It is most probable that the fragments of metal originated from the second-stage outlet cover that burst during the over-pressurization of the compressor.

1.3.1 Crew Trauma

In the 48 hours after the accident, a plethora of officials including inspectors, investigators, Class surveyors, police, owner's and insurance representatives visited the vessel. All had many questions in order to satisfy their mandates, and the senior officers--particularly the master and chief engineer--were heavily solicited. Given the seriousness of the situation, this was to be expected, but reportedly increased the stress and anguish already being suffered by the crew.

1.4 Damage to the Vessel

The No. 3 compressor, which is of the non-oil-free, reciprocating, water-cooled type, was damaged beyond cost-efficient repair. The second-stage air cooler cover was burst and fragments of this piece were projected outward at high velocity in a shrapnel-like fashion. Other damage to the compressor included burst cooler tubes in the second-stage (after) cooler, burst compressor casing in way of the cooling water chamber and a flayed flexible delivery air line. Of the 33 second-stage cooler tubes, 18 were found to be ruptured.

1.5 Certification

1.5.1 Vessel

The last annual survey of the "CANMAR SPIRIT" was at Rijeka, Yugoslavia, on 09 September 1998. The Cargo Ship Safety Construction Certificate was issued at London on 16 August 1996 and was due to expire on 14 May 2001. The Cargo Ship Safety Equipment Certificate was issued at Hong Kong on 11 June 1997 and was last endorsed at Montreal on 12 June 1998.

1.5.2 Personnel

The victim held a certificate of competency to perform the duties of a ship's greaser issued on 01 October 1996 with the endorsement issued in December 1997. He also held a firefighting certificate, a certificate of ability for handling lifesaving appliances, and a certificate of search, rescue and survival at sea as per the International Convention on Standards of Training, Certification and Watchkeeping for Seafarers, 1978.

The chief engineer held a first class engineering certificate issued in 1989. The most recent continued proficiency endorsement was acquired in 1997.

The master held a master mariner certificate issued in 1972. The most recent continued proficiency endorsement was acquired in 1997.

All of the above certificates were issued by the Ministry of Maritime Affairs, Croatia.

1.6 Personnel History

The duty greaser killed by the burst compressor had joined the "CANMAR SPIRIT" on 09 December 1998, seven weeks before the accident. He had been assigned the 1200 to 1600 watch and was considered a dependable employee and conversant about engine-room procedures. He had previous experience operating the compressors and was knowledgeable about the start-up procedures. It was his first tour of duty on board the "CANMAR SPIRIT".

The master had been at sea since 1965, and had acted as master on various ships since 1978. He had joined the "CANMAR SPIRIT" on 13 January 1999 for the first time.

The chief engineer had been employed in a seafaring capacity since 1977, and as chief on various vessels since 1996. He had joined the vessel on 09 December 1998 for the first time.

1.7 Laboratory Examination and Testing

1.7.1 Non-Return Valves and Relief Valves

All three compressors on board the "CANMAR SPIRIT" are equipped with non-return (check) valves. The function of the non-return valve is to prevent the reverse flow of air from the air receiver back to the compressor. Upon examination, it was found that the non-return valve on each of the three compressors was not functioning correctly, thus allowing high-pressure air to leak back into the compressor.

The compressors are also equipped with low- and high-pressure relief valves on the first and second stages respectively. They are of the plunger and spring variety and are adjusted to open at 10 per cent above their associated stage operating pressure. Upon examination and testing of the failed compressor's relief valves, it was found that the second-stage relief valve was completely blocked on the inlet side by burnt oil residues, and at least 50 per cent blocked on the outlet side by similar residues. In this condition, it is highly unlikely that the valve would have functioned properly. The first-stage relief valve was damaged during the compressor failure by flying debris and was not tested, but a visual examination showed it to be completely blocked by oily, sooty residues.

The relief valves from the other two compressors were also examined and tested. Only one first-stage and one second-stage valve worked as specified, giving an overall failure rate of slightly more that 66 per cent (four out of six relief valves failed to work properly). The malfunctions are attributable to an oily, sooty build-up.

1.7.2 Jabsco Water Pump

The Jabsco cooling water pump from the failed compressor, which supplies water to the first- and second-stage air cooler cylinder jackets and cylinder heads, was disassembled and examined. Four of the nine impeller vanes had fractured off, two of which were found jammed between the impeller and the pump housing. A fifth vane was very close to complete fracture. The vane fracture surfaces were examined under magnification and revealed an appearance consistent with a failure having occurred through a period of time, and not as a result of the compressor failure.

1.7.3 Second-Stage Air Cooler Cover

The second-stage air cooler cover contains a drain valve, a fusible plug and the high-pressure relief valve. At the time of the failure, this cover fractured into many pieces that were projected outward at high velocity. An optical microscope examination revealed fracture surfaces consistent with a brittle mode of failure such as would be present in an instantaneous overstress. No evidence of pre-cracking was observed.

1.7.4 First- and Second-Stage Air Cooler Tubes

While none of the first-stage cooler tubes had failed, 18 of the 33 tubes that make up the second-stage tube nest failed in a manner consistent with an over-pressurization. Microscopic examination revealed no evidence of pre-cracking on the fracture surfaces of the tubes. Also, there was no indication of overheating or any evidence of combustion as would be expected subsequent to an explosion-type occurrence. The evidence therefore points to a bursting-type occurrence.

Close examination and testing of both first-stage and second-stage air cooler tubes indicate that the first-stage tubes met manufacturer's specifications but the second-stage tubes did not. Specifically, the manufacturer specifies copper tube BS2871 which contains a minimum of 99.85 per cent copper and a wall thickness of 0.91 mm for both first- and second-stage tubes. The composition of the second-stage tubes installed on the compressor was found to be consistent with a UNS C68700 aluminum brass alloy, with wall thicknesses on average only half that of manufacturer's specifications.

Furthermore, a close examination of these tubes revealed corrosion pitting that can be attributable to the absence of anti-oxidant additives in the cooling water.

1.8 The Compressor

The No. 3 compressor was a Hamworthy type 2TM63 made in 1976 with a rated capacity of 350 cubic metres/hour at a pressure of 29.3 bar. This compressor was of the non-oil-free, reciprocating, two-stage water-cooled type. As of the end of December 1998, ship records indicate that the total number of running hours on the compressor was 48,002.

2.0 Analysis

2.1 The Compressor System

2.1.1 Operational Procedures

During the examination and testing of the various components of the failed compressor and the two other compressors, the non-return valves on all three compressors were found to be leaking. This was attributable to their being blocked by sooty, oily residues. With the non-return valves inoperative, manual intervention was necessary; in particular, the opening of the individual system delivery valve for the required compressor before start-up and the closing of these same valves subsequent to the termination of compressor operation.

2.1.2 Start-up Procedure

An examination of the compressor flats area after the accident provided clues as to the actions of the duty greaser while starting compressor No. 3. Most importantly, it was found that the system delivery valve for compressor No. 3 had remained closed during the start-up procedure. It seems likely that the duty greaser forgot to open this valve at the beginning of the start-up procedure. This oversight was made even though he was conversant with the start-up procedure, had started the compressors repeatedly on this ship since joining the vessel, and had just successfully started compressor No. 1. The duty greaser quite possibly experienced what could be described as "mode error." This type of error occurs when a situation is falsely classified, and the resulting actions are inappropriate. This error often occurs when the mode in which the equipment is operating is not visible, and the information provided to the operator is ambiguous. The system delivery valve remained in the closed position and this was not visible at the compressor itself. This omission was one of the primary elements leading to the severe over-pressurization of the compressor.

2.1.3 System Design

Simply defined, a system is an entity that exists to carry out some purpose.Footnote 4 A system is composed of humans, machine and other things that interact to accomplish a goal. Basic principles of systems design seek to reduce error by eliminating opportunities for operators to produce error within the system, by making errors visible and reversible and by mitigating error consequence. Every interaction between the operator and the machine (any type of physical object) within the system provides an opportunity for human error. For those operator-machine interfaces that are considered essential, it is imperative that the operator be able to control the machine. In order to do this, the user must know the state the machine is in and must be able to change that state or effect change. These two tasks are carried out by means of displays and controls respectively.Footnote 5 There was no indication at the compressor that the system delivery valve was still closed. Furthermore, manual intervention could have been avoided had the non-return valves been operating as designed and the compressors configured for automatic operation. Automatic control for air compressor is not mandatory on this class of vessel.

2.2 Replacement Parts

2.2.1 Second-Stage Cooler Tubes

After examination and testing of the second-stage cooler tubes, it was determined that these tubes did not meet manufacturer's specifications with respect to material, outside diameter and wall thickness. When tubing that met manufacturer's specifications was tested to destruction, the burst pressure was found to be 7,000 pounds per square inch (psi). Similar testing of the second-stage cooler tubes resulted in a burst pressure of 4,000 psi.

While this does not appear to be a direct cause or underlying factor for this accident, it does highlight the fact that significantly inferior replacement parts were used to renew the second-stage cooler tubes. Past experience has shown that serious compressor accidents have occurred on ships due to the installation of sub-standard replacement parts.

2.3 Maintenance Issues

2.3.1 Jabsco Pump

Since the fusible plug on the high-pressure delivery cover was in good condition, this would indicate that there was no overheat condition. It is therefore likely that the pump was still functioning, although most probably at reduced capacity, at the time of the accident. This element of the compressor is not at cause.

2.3.2 Relief Valves

The relief valves were found to be clogged with oily, sooty residues. In all likelihood these residues were due to the lubricating oil used in the compressor migrating past the piston rings and thus present in atomized form in the compressed air. There was no evidence to indicate that a regular verification of the efficacy and calibration of the relief valves took place on board the vessel, aside from the statutory inspection once every five years. These valves are normally calibrated by the manufacturer to open at 10 per cent in excess of the working pressure of the stage in question. The manufacturer's recommended maintenance schedule suggests lifting the water jacket relief valve every three months or after 250 hours of use. There is, however, no mention by the manufacturer of any verification regime for the air relief valves and no "on-site" method available to the crew to undertake a proper verification of relief valves of this design.

2.3.3 Non-Return Valves

The non-return valves were also found to be clogged with similar oily, sooty residues as were found on the relief valves. The manufacturer's recommended maintenance schedule for the non-return valves states that they must be cleaned and inspected every six months or after 500 hours of use. There was no documentary evidence to substantiate that the recommended maintenance was undertaken by the ship's crew. The fact that the non-return valve on the failed compressor, as well as on each of the other two compressors, was not functioning according to manufacturer's specifications indicates that such maintenance was most likely not carried out. Underlying factors in the cause of the accident were the malfunctioning of the non-return valves and the fact that the compressors were not configured for automatic operation. Because this was the case, a human intervention and presence was necessary in the area to start the equipment.

2.3.4 Cooler Tubes

Under magnification, the second-stage cooler tubes displayed evidence of corrosion pitting on the outer surfaces. The tubes had an oxidized appearance and tube thickness was not uniform. It was determined that the use of anti-oxidants in the cooling water was less than adequate and this contributed to an undue corrosion of tubes. Although not mentioned in the manufacturer's manual, the addition of anti-oxidants to the cooling water is considered consistent with current best practices.

2.4 Statutory Regulations and Testing

2.4.1 Regulations

The "CANMAR SPIRIT" is a Hong Kong-registered vessel and, as such, subject to Hong Kong maritime safety legislation. Regulation 27(2)(b) of the Hong Kong Merchant Shipping Regulations (MSR) states that:

Means shall be provided in any such ship to prevent overpressure in any part of any such compressed air system and, where water jackets or casings of air compressors and coolers might otherwise be subjected to dangerous overpressure due to leakages into the air pressure parts, suitable pressure relief arrangements shall be provided.

Furthermore, Regulation 77(1)(a) of the MSR states:

the condition of the ship and its equipment is maintained so as to comply with the relevant provisions of these regulations.

Canadian regulations concerning compressed air systems, such as Schedule XI of the Marine Machinery Regulations, state very similar rules as regulation 27(2)(b) of the Hong Kong MSR. This is also consistent with the International Convention for the Safety of Life at Sea (SOLAS), chapter II-1, regulation 34.1. Additionally, the Canadian regulations call for periodic general inspections of air compressors and their components not exceeding five years.

However, neither Canadian nor Hong Kong regulations contain a systematic requirement to have the relief valves tested and/or re-calibrated. In fact, the Canadian regulations leave it up to the inspector's discretion to undertake this verification. Specifically, part IV, division I of Schedule XI states:

For air and refrigeration gas compressors and air driven machinery, where applicable and, in the opinion of the inspector, practicable, verification that the compressors, air driven machinery, cooling systems, control, monitoring alarm and safety devices are in correct adjustment and operational condition.

2.4.2 Testing

Under normal circumstances, the Cargo Ship Safety Construction Certificate is endorsed every year and re-issued every five years. Integral to this renewal is the inspection of all safety devices such as relief valves. The Cargo Ship Safety Construction Certificate of the "CANMAR SPIRIT" was issued in London on 16 August 1996 and it was endorsed at Rejeka, Croatia, on 09 September 1998.

Insofar as the relief valves on the compressors of the "CANMAR SPIRIT", the survey as completed in 1996 was carried out by an exclusive Lloyd's Register surveyor. The normal survey requirement is to examine the compressor parts in the stripped down condition and subsequently carry out a running test to verify the safety devices. In order to respect the intent of the regulations, including SOLAS chapter II-1, regulation 34.1, and provide means to prevent over-pressure in the compressor system, the relief valves must be able to operate as designed. If, inherent in the design of these valves, there is no means for Class inspectors or ship's crew to verify their efficacy while in place on the compressor, there should be a requirement to have them tested by a competent authority and accompanied with a certificate of test at intervals that will guarantee their proper operation.

2.5 Crew Rotation

An argument can be made that one criterion for a vessel to be operated safely, on a consistent basis, is the requirement that the crew have in-depth knowledge of the structure and interdependence of various elements within the system. This in-depth knowledge can only be gained through time spent on the vessel, and this result is obtained through the use of a consistent core crew for any given vessel.

While the mariners aboard the "CANMAR SPIRIT" had extensive sea experience, their experience on board this vessel was limited. The victim had joined the vessel 49 days before the accident and he had no prior work experience on board the "CANMAR SPIRIT". It was also the first tour of duty on this particular vessel for both the master and the chief engineer, although the former had had one tour of duty on a sister ship a few years previously. Of the seven other engine-room crew members, five were on their first tour of duty on the vessel, one of whom had previous experience on a sister ship. The remaining two were on their second tour of duty aboard the "CANMAR SPIRIT".

While rotating crews are more or less the norm in the marine trade today, there are drawbacks associated with high crew rotation on a particular vessel. A lack of continuity of personnel, especially in management positions such as that of master and chief engineer, can lead to a reduced leadership role for these officers. Another negative effect could be a lack of insight respecting the particular needs of the vessel. Crew members, including senior officers, on the vessel for one tour and then onto another vessel for the next tour tend to "put out the fires." Long-term preventative maintenance, attention to detail and an intimate knowledge of the particular ship tend to be less than that for a vessel with a relatively stable crew.

Although the International Convention on Standards of Training, Certification and Watchkeeping for Seafarers, 1978 (STCW) ensures a uniform standard of competence, it only speaks to crew familiarisation in respect to emergency situations. The STCW does not address the issue of in-depth familiarisation for a particular vessel nor maintenance issues. Section 10 of the International Safety Management (ISM) Code tries to rectify some of these shortcomings by introducing the necessity of maintenance standards. Although compliance with the ISM Code is not mandatory for container ships until 1 July 2002, the "CANMAR SPIRIT" and its managers were already in compliance and the ship had been issued a Safety Management Certificate.

2.6 Post-Occurrence Support

Despite the increased demands on the crew following the accident, assistance to deal with stress reaction, shock or post-traumatic stress disorder was neither requested nor forthcoming. However, there was no other known incident which resulted from such adverse psychological effects. Section 8 of the ISM Code requires that a Company's Safety Management System provide measures to ensure prompt response to accidents, hazards and emergency situation involving its ships, but does not specifically address psychological post-accident support. Such support, if in place, would contribute to the well-being of the crew and better assure an individual's performance and contribution to safety.

3.0 Findings

3.1 Findings

  1. The duty greaser started the No. 3 compressor without opening the system delivery valve for this compressor.
  2. The pressure relief valves on both the first and second stages of the failed compressor were blocked by sooty, oily residues and thus rendered inoperable. On the other two compressors, half of all the relief valves did not work properly, when tested, due to similar residues.
  3. The non-return valves on all three compressors leaked, thus allowing compressed air to return to the compressors from the air receivers when the compressors were not operating. This created the necessity for human intervention since the delivery valves had to be opened and closed manually before and after each compressor start and stop sequence.
  4. The seat and spring plates of the failed compressor's non-return valve appeared to be in good condition; however, there was an extensive build-up of oily, sooty residues in the valve. This is the most probable cause of the leaking condition.
  5. The Jabsco water pump had been operating at reduced capacity due to five previously broken impeller vanes, but no evidence of overheating was observed.
  6. The fracture surfaces on the second-stage outlet cover were consistent with an instantaneous failure with no evidence of pre-cracking or previous repair. The cover fractured into many fragments that were projected outward at high velocity.
  7. The duty greaser sustained fatal injuries from fragments of metal projected out at high velocity.
  8. The first-stage cooler tubes were consistent with manufacturer's specifications in all respects. They did not fail subsequent to the over-pressurization of the compressor.
  9. Of the 33 second-stage cooler tubes, 18 failed during the over-pressurization of the compressor.
  10. The second-stage cooler tubes did not meet manufacturer's specifications with respect to material, outside diameter and wall thickness. Wall thickness was found to be, on average, half that of manufacturer's specifications.
  11. The second-stage cooler tubes showed no evidence of overheating or combustion. The over-pressurization was most likely due to the compressor working against a closed circuit created by relief valves not operating properly and a closed system delivery valve.
  12. The cooler tubes revealed corrosion pitting attributable to the less-than-adequate use of anti-oxidant additives in the cooling water. This does not seem to be a significant factor in this accident.
  13. The compressor casing burst open in way of the cooling water chamber due to a severe and near instantaneous over-pressurization. The cooling water relief valve seems to have been operable but in all likelihood could not handle the rate of expansion associated with the complete and near instantaneous failure of the high-pressure cooler tubes at pressures at or above 4,000 psi.
  14. The majority of the engine-room crew and the master were experienced mariners but this was their first tour of duty on board the "CANMAR SPIRIT".
  15. Some of the crew members reported being under pressure and stress following the accident but relief and assistance were neither requested nor offered.

3.2 Causes anc contributing factors

The No. 3 compressor on board the "CANMAR SPIRIT" experienced a severe and near instantaneous over-pressurization due to the system delivery valve remaining closed while the compressor was started. This omission, combined with the malfunctioning air relief valves, created a closed circuit in which certain components of the compressor could not withstand the ever-increasing pressure. Contributing to the accident was the less-than-adequate maintenance of non-return valves.

4.0 Safety Action

4.1 Action Taken

Before the vessel was cleared to depart, Transport Canada required that correctly calibrated safety relief valves be installed on all working compressors.

The flexible high-pressure air delivery line was renewed on compressor No. 1.

The company requested that the remaining compressors (1 and 2) be re-certified with a maximum allowable working pressure of 23 bar, down from 29.3 bar. This was done once it was demonstrated that the performance requirements were respected concerning main engine activation at this reduced pressure. Permanent indications as to this new working pressure were installed close to each compressor nameplate within 14 days.

New pressure gauges on the remaining compressors were to be installed within 14 days.

Shortly after the accident, the management company issued a safety message to all vessels under its management informing mariners that the statutory inspection of relief valves and pressure bursting devices is no guarantee of their effectiveness between surveys. Additionally, the message required that all safety devices for pressurized devices be inventoried, checked for manufacturer's specifications and sent ashore for examination, testing and re-calibration if necessary, and be accompanied by a certificate of test. The directive goes on to specify that annual examination and testing of these devices is considered a minimum. Also, the directive requires that the planned maintenance system be amended to record the maintenance of safety systems. Other directives within the safety message include the posting of operating instructions adjacent to pressurized systems, thorough training of crew members in the use and hazards of such systems, and the testing of pressure alarms and shutdowns, where installed, at intervals not exceeding three months.

The owners advise that the welfare of crew members affected by any emergency situation must be seriously considered and intend to account for such mental anguish in their emergency scenario checklists.

Following the accident, Lloyd's Register issued Technical Report No. 12 in their publication "Marine Bulletin" which requires Lloyd's Register surveyors, when surveying air compressors and air receivers, to give particular attention to all safety devices and, in particular, the correct functioning of relief valves is to be witnessed. The condition and accuracy of pressure gauges should also be checked. The report also urges shipowners and operators to follow manufacturers' recommendations for the operation of this machinery.

The flag state, Hong Kong, also investigated the occurrence producing similar findings and the following recommendations:

An information document e.g. Marine Department Notice, should be prepared by the Hong Kong Marine Department to invite all concerned parties' attention (including local maritime education & training institutions) towards the proper maintenance of shipboard pressure equipment, particularly the regular maintenance and testing of its safety devices.

Due to the doubtful shipboard maintenance standard as evidenced in the investigation, it is recommended that Hong Kong Marine Department should conduct a Flag State survey and audit, both to the company and the vessel ... to assess the safety management system of the ship manager and the vessel. A copy of the report together with a warning letter is to be forwarded to the Chief Engineer stressing that as a qualified engineering officer, it is his duty to supplement any shortcomings found in the maintenance program.

A copy of the (Hong Kong) Report is to be forwarded to the shipowner and ship manager informing them that they should ensure the correct functioning and maintenance of all the pressure equipment fitted on board their ships. A copy of the Report is to be forwarded to Lloyd's Register of Shipping for their information.

A copy of the (Hong Kong) Report is to be forwarded to the compressor manufacturer to invite them to enhance their recommended Maintenance Schedule.

This report concludes the Transportation Safety Board's investigation into this occurrence. Consequently, the Board authorized the release of this report on .

Appendices

Appendix A— Photographs

Photo 1. - Fractured compressor water jacket casing after removal of coolers
Fractured compressor water jacket casing after removal of coolers
Photo 2. Burst high pressure air cooler tubes and fractured casing
Burst high pressure air cooler tubes and fractured casing
Photo 3. Damaged compressor showing burst air cooler and cover
Damaged compressor showing burst air cooler and cover

Appendix B— List of Supporting Reports

The following TSB Engineering Branch Report was completed:

This report is available upon request from the Transportation Safety Board of Canada.

Appendix C— Glossary

EST
eastern standard time
IMO
International Maritime Organization
ISM
International Safety Management
kW
kilowatt(s)
m
metre(s)
MCTS
Marine Communications and Traffic Services
mm
millimetre(s)
MSR
Merchant Shipping Regulations
OOW
officer of the watch
psi
pound(s) per square inch
SI
International System (of units)
SOLAS
International Convention for the Safety of Life at Sea
STCW
International Convention on Standards of Training, Certification and Watchkeeping for Seafarers, 1978